Question: which is optimal value in the case of job sequence problem item : 1 2 3 4 5 6 7 profit : 3 5 20 18 1 6 30 deadline : 1 3 4 3 2 1 2

Answer:

MCQ: which is optimal value in the case of job sequence problem item : 1 2 3 4 5 6 7 profit : 3 5 20 18 1 6 30 deadline : 1 3 4 3 2 1 2

Correct Answer: A. (1,5,6,4)

Discuss a Question

Related Questions

You may be interested in:

Data Structure Multiple Choice Questions And Answers (MCQs)

Recently Added Articles

How Image to Text Conversion Make Printed Study Materials Easier to Use?

Last updated on: October 23, 2026Posted by: ExamRadar

7 Best Online Exam Makers for Teachers, Schools, and Businesses

Last updated on: October 21, 2026Posted by: ExamRadar

How to pick a Bintan resort when you’ve only got 48 hours

Last updated on: September 23, 2026Posted by: ExamRadar

Features to Look for While Choosing the Best Automation Tool

Last updated on: July 15, 2026Posted by: ExamRadar

AI vs Machine Learning: Key Differences Every Professional Should Know

Last updated on: February 13, 2026Posted by: ExamRadar

Office Cleaning Services That Elevate Sydney Offices

Last updated on: February 11, 2026Posted by: ExamRadar